Next Section of 17th Street South to Close Monday

07/02/2020


  • Upcoming Traffic Pattern Map
    Upcoming Traffic Pattern Map

Zone: South
Project: 17th Street South Improvements

Beginning Monday, July 6, after 7 a.m., contractors plan to begin work on the next section of the 17th Street South road and watermain improvement project. Crews will shift project work north to the middle section of phase two work on 17th Street South between 21st Avenue to 25th Avenue South.

Work on 17th Street South is divided into three sections to maintain residential access as much as possible. Over the next few months crews will continue to work their way north towards 21st Avenue South.

Once traffic control is in place, motorists can expect:

  • Second section of 17th Street South fully closed to traffic and access will be from the north at 21st Avenue South or the south at 25th Avenue South

Project work is near completion in the south section of 17th Street South. Weather permitting, crews plan to reopen this section of road ahead of the weekend.

Phase work may overlap, and multiple phases may be under construction at the same time. Project work is split into the following phases:

  • Phase One: 25th Avenue South between 18th Street to 16th Street South
    • 25th Avenue South between 16th Street and 17th Street will be closed for a short duration of two weeks to accommodate storm sewer installation.
  • Phase Two: 17th Street South between 21st Avenue to 25th Avenue South
    • Work on 17th Street South will be divided into three sections to maintain residential access as much as possible.
  • Phase Three: 25th Avenue South between 18th Street to 14th Street South
    • Temporary lane closures will be in place during the mill and overlay portion of this project.

Pedestrian access will be maintained throughout each phase of project work. Access to some driveways will be restricted during construction activities. Side streets and avenues will need to be utilized during these times.

The purpose of this project is to upgrade portions of the City’s infrastructure in this area including water main, sanitary sewer, storm sewer, pavement, curb and gutter, sidewalks, and street lighting.

The reconstruction of the 17th Street South roadway is necessary due to the deterioration of the existing street section, which was installed in 1972 with street patching done throughout the years. A mill and overlay on 25th Avenue South will provide a new wearing surface as well as correct deficiencies which have appeared over time.

Please remember to slow down and watch for trucks entering and exiting the work area.

The project work should be complete by early October.