Menu

FargoStreets Hero Image

7th Avenue and 4th Street North Intersection Slated to Open Saturday, August 22

08/20/2020


  • 7th Avenue and 4th Street North intersection reopening to traffic
    7th Avenue and 4th Street North intersection reopening to traffic

Zone: North
Project: 7th Avenue North Improvements

By the end of this weekend, contractors for the City of Fargo’s 7th Avenue North road and watermain improvement project will reopen the 4th Street and 7th Avenue North intersection. Once the intersection is fully reopened to north and south traffic, crews will continue to finish remaining items along 7th Avenue North.

By late evening Saturday, August 22, motorists can expect the following traffic control to be in place:

  • 4th Street North intersection open to north and south traffic
  • 7th Avenue North closed between east of Broadway to the alley west of 2nd Street North, with the exception of the 4th Street intersection
  • Broadway intersection open to north, south, and west traffic
  • Pedestrian access maintained on the north side of the roadway with north/south crossings at the intersections of Broadway and 2nd Street North
  • Traffic will be detoured via Broadway to 6th Avenue North to 2nd Street North

Access within the work zone will be restricted, but the contractor will ensure business and residential access is maintained via alternate routes and parking lots as much as possible.

Over the next few weeks, the contractor will continue working on finishing street lighting, traffic signals, pavement marking, permanent signing, and landscaping. Weather permitting, crews plans to remove all traffic control and fully open 7th Avenue North to traffic by the end of August.

Project work may overlap, and multiple phases may be under construction at the same time. Construction will be split into the following phases:

  • Phase 1: 7th Avenue North from Broadway to the alley west of 2nd Street
    • Phase 1A - Broadway and 7th Avenue intersection
    • Phase 1B - 4th Street and 7th Avenue intersection

Phases 1A and 1B cannot be under construction at the same time but must be completed within the 110 days of starting Phase 1. The 2nd Street and 7th Avenue North intersection will remain open throughout the project with only minor work taking place in the southwest corner to install concrete in the boulevard.

The purpose of this project is to upgrade portions of the City’s infrastructure in this area including water main, sanitary sewer, storm sewer, pavement, curb and gutter, and traffic signals.

This stretch of roadway has aging pavement and underground utilities that have been subject to numerous unscheduled repairs through the years. The project will include up-sizing the water main on 7th Avenue North to 16" diameter pipe between 4th Street to Broadway. The up-sized pipe, in conjunction with various water tower upgrades, is a critical component in providing north Fargo with a reliable water supply.

Please slow down and watch for trucks entering and exiting the work area.

View All Updates