14 1/2 Street North Improvements


Zone: NorthWhat zone am I?

Completed

Start: Spring 2022

Estimated Completion: Summer 2023

Current Status:

This project is substantially complete.


14 1/2 Street North Overall Map

Overall Project Map


Project Overview:

This project is for roadway improvements on 14 ½ Street North between NP Avenue and 1st Avenue and NP Avenue North between 14th Street and 14 ½ Street.


April 13th, 2022 Public Information Meeting


Impacts:

14 ½ Street will be closed to thru traffic. Local traffic will be maintained throughout the project in one direction at all times.


Contractor:

Master Construction


Timeline:

This project is anticipated to be constructed during the 2022 construction season.


Funding:

This project will be funded with Special Assessments and City Funds.


Purpose:

This project will turn 14 ½ Street North between NP Avenue and 1st Avenue and NP Avenue North between 14th Street and 14 ½ Street from a rural gravel section to an urban pavement section with curb and gutter, street lights, sidewalks and incidentals.