Menu

FargoStreets Hero Image

Seal Coat Project: 2022


Zone: North, SouthWhat zone am I?

Completed

Start: June 2022

Estimated Completion: End of July 2022

Current Status (Updated 10/3/2022):

This project is substantially complete and fully open to traffic.


SealCoat_2022_OverallMap

Overall Map


Project Overview:

This project is part of the City's annual infrastructure improvement efforts and impacts multiple areas of Fargo each construction season. Seal coat projects extend the life of asphalt pavement and provide a more traffic and weather resistant surface. It involves spraying an asphalt emulsion on the pavement surface, immediately followed by a rock chip application that is embedded into the emulsion. The 2022 project will take place in 10 different areas.


Impacts:

Traffic will be maintained during construction, but short-term lane closures and parking restrictions are required to safely accommodate construction activity.

Construction activity will be performed in multiples areas of the City. To view the affected areas, please refer to the Overall Project Map via the Project Resources section on the right side of this page.


Contractor:

Pearson Bros. Inc.


Timeline:

This project is scheduled to start in June (after 6/6) or July of 2022 and be completed by the end of July 2022.


Funding:

This project will be funded by Street Sales Tax Funds and Special Assessments.


Purpose:

The annual seal coat project extends the pavement life of our City streets and helps prevent future wear from weather and traffic. This preventative maintenance ultimately saves residents and the City money, time, and resources.